Now there are a lot of families in the decoration of the time will add an underground waterproof project, but there are a lot of people do not know the underground waterproof engineering technical specifications of the new increase in the construction method is what!
What is the new construction method of underground waterproof engineering technical specification?
1. The construction method of "pre-laying and anti-sticking" is advocated for polymer self-adhesive film coils, which can be laid on a flat, firm, damp base surface without obvious water accumulation. This construction method can not only speed up the construction progress and shorten the construction period, but also help prevent the common problem of leakage caused by water channeling between the waterproof layer of coils and the base layer.
2. When laying the waterproof layer of polyethylene polypropylene composite coil, it is clearly required to use the polymer cement bonding material matched with it, and the bonding area shall not be less than 90%.
3. When laying the waterproof layer of plastic waterproof board, the construction measure of "it is appropriate to set up a partitioned embedded grouting pipe system" is added, which is conducive to avoiding the occurrence of a water leakage caused by water channeling and the disease of the whole line.
4. The design and construction of the waterproof layer of bentonite waterproof material are clearly and specifically stipulated to ensure the waterproof quality of the material in underground engineering.
5. In order to meet the needs of full development and utilization of underground space, the design and construction of waterproof and drainage of underground engineering planting roof have made specific provisions. The new specification emphasizes that the planting roof should be in the ordinary waterproof layer must be laid on a layer of resistance to root puncture waterproof layer.
6. In view of the pile head waterproof treatment problems more, the new code for the pile head waterproof construction clear material should be with the base has good adhesion, moisture curing and should be connected with the cushion waterproof layer. For the use of cement-based permeable crystalline waterproof coating, should be in a solid, clean, wet base, continuous and uniform brushing, and shall not be less or leakage coating, and should be timely spray water conservation.
7. The outer waterproof coating of shield tunnel segment advocates the use of high permeability modified epoxy coating or cement-based permeable crystalline waterproof coating with permeable self-healing materials.
8. The performance index requirements of concrete expansive agent for post-cast strip shall meet the requirements of Table 4.8.
9. In the waterproof layer of cement mortar, the provisions on "ordinary cement mortar" and "use strength grade shall not be less than 32.5MPa cement" in the original specification are deleted.
10. In the polymer emulsion, the provisions of the original specification that the solid content should be greater than 35% and special products should be selected have been deleted, and the quality should be in line with the provisions of the current national standard "polymer emulsion for building waterproof coating", so as to coordinate with the material standard.
11. In the polymer cement waterproof mortar, the content of "should be used up within 1h after mixing" is deleted, and the requirement of "should be used up within the specified time" is changed to make it more in line with the actual construction situation.