[Technical Dry Goods] Hongyuan Waterproof teaches you how to practically apply the coated roll composite waterproof system

Release time:

2024-06-06 16:31

The Liujing Building is located in Pyongyang, the capital of North Korea, named after Pyongyang's ancient name "Liujing.
Construction of Liujing Building started in 1987, was interrupted in 1992 due to financial difficulties, and resumed in 2008 due to investment from Egyptian enterprises. Because it has not been completed for many years, the Liujing Building has been ridiculed by foreign media as "the world's largest unfinished building". The overall structure is triangular pyramid, slope angle of 75 degrees, a total of 105 layers, 330 meters high.
The 3000-room super building is planned to become one of the tallest hotels in the world and will become a landmark building in Pyongyang.
Its waterproof design is provided by Hongyuan Waterproof.
Application Materials:Hongyuan Waterproof Two-component Polyurethane Waterproof Coating EPDM Waterproof Membrane
Project area: The roof area is divided into 3 areas, each area is about 15000 square meters.
Original roof design structure (from bottom to top):
Cast-in-place reinforced concrete roof slab → 2% slag roof sloping layer → 20mm thick 1:3 cement mortar leveling layer → "3 cloth 4 coating" asphalt oil, sand spreading protection on the surface
design optimization
Optimized roof structure
1. Vapor barrier:
The new scheme is designed to construct a 1.5mm thick polyurethane waterproof coating film vapor barrier layer first. The coating film is closely combined with the base surface without seams, and can play a good dual effect of vapor barrier and auxiliary waterproof.
Surface condition of cast-in-place concrete roof slab after formwork removal
2. Thermal insulation layer:
A thermal insulation layer is paved over the vapor barrier layer, and an 80mm thick extruded board (xps) is adopted, and a 30mm thick 1:2.5 cement mortar leveling layer is made on the extruded board for protection, which plays a protective role for the thermal insulation layer and a connecting carrier role for the waterproof layer in the next process.
3. Polymer waterproofing membrane layer:
Due to the large temperature difference in the northeast climate, severe cold in winter and low temperature, in order to improve the waterproof performance, it was changed to a high-temperature vulcanized EPDM rubber waterproofing membrane. The material meets the GB18173.1--2012 "polymer waterproof material part 1: sheet" standard requirements, coil aging resistance, long service life, excellent resistance to high and low temperature performance, tensile properties, the shrinkage of the grass-roots deformation and cracking adaptability and other characteristics; the use of full adhesive paving, to ensure the roof waterproof effect.
4. Fine stone concrete protective layer:
In view of the northeast climate and the human roof, it is changed to 50mm thick inner reinforcement (Φ 6) fine stone concrete protective layer. And set 6m × 6m separation seam, seam width 20mm, seam embedded with modified asphalt sealing material, can play a sealing, anti-expansion, anti-freeze-thaw effect.
Construction process
1.Vapor barrier construction
1. Grass-roots treatment
Check the base surface before construction, requiring that the dry humidity is not more than 9%, the base surface is cleaned up, smooth, dense, firm, free of sand, cracks and other hole defects. If there are defects, repair them with polymer cement mortar, and the parts to be treated and the whole base layer meet the specification requirements and pass the acceptance, the next process can be carried out.
Polymer cement mortar for base course repair
2. Construction of polyurethane coating vapor barrier
1) Preparation of two-component polyurethane waterproof coating
The polyurethane waterproof coating used in this project is two-component, and the mass ratio of A and B components is 1:2. After pouring component B into the barrel according to the proportion, add component A, and stir for 3-5 minutes with a special stirrer until the mixture is uniform and free of bubbles. Polyurethane waterproof coating shall be prepared with the use of special personnel, so as to avoid long-term use, reaction thickening, affecting the construction effect.
Two-component polyurethane mixing ratio
2) Subcoating construction
Use rubber scraper to paint evenly on the base, the direction is consistent, the thickness is uniform, not exposed, the construction thickness of 0.5mm.
Bottom coating construction
3) 2nd coating construction
After the primer is completely cured (not less than 24h), the second coating construction shall be carried out, and the configured coating shall be evenly scraped with a rubber scraper, the direction shall be perpendicular to the first coating, and the coating thickness shall be 0.5mm.
The second time polyurethane coating construction
4) The third coating construction
After the second coating film is completely cured (not less than 24h), the third coating film shall be applied, which is also perpendicular to the previous coating film, with a coating thickness of 0.5mm. The coating construction requires multiple times of brushing (not less than 3 times, and the details such as pipe root and gutter shall be coated multiple times) to reach the design thickness requirements.
The third coating construction
3. Water storage test
After the polyurethane waterproof coating is cured, the water will be stored for 24 hours. If the roof area is large, the water level will be 20mm higher than the high point, and no leakage will be considered as qualified.
Hoist tap water (left), block and store water in sub-sections (right)
2.Construction of thermal insulation layer
1. After the vapor barrier layer is accepted, 80mm thick XPS insulation board shall be laid as the roof insulation layer, and the short side of the insulation board of the same layer shall be laid at staggered joints.
2. After the laying of XPS insulation board, the construction of 30mm thick cement mortar protective layer. Paving cement mortar on the insulation board, rubbing and compacting with wood trowel to ensure that the thinnest part shall not be less than 30mm, the mortar protective layer shall be compacted and leveled for secondary calender treatment, and watering and curing shall be carried out after 24 hours at normal temperature. The curing time is generally not less than 7d; Waterproof layer construction can be carried out after drying.
Insulation layer paving and cement mortar protective layer construction
3.Construction of waterproof layer
1. Basic requirements
1) The base shall be flat, solid, clean and dry (water content shall not be greater than 9%) without dust and sand;
2) Roof sinkhole, gutter, pipe root and other parts of yin and yang angle shall be painted into circular arc with R≥ 50mm;
3) The roof slope, leveling and detail nodes meet the requirements of the design specifications, and the pipe fittings and other facilities penetrating the roof panel shall be installed and fixed in place.
2. Construction of EPDM waterproofing membrane
1) Open the multi-roll coil and place it flat on the roof for drying for not less than 1h to release the curling stress generated by the coil in production.
Open the coil to dry
2) According to the roof slope, determine the coil laying position from the lowest point of the running water gutter. The long side of the coil should be overlapped along the running water direction, pop up the laying starting line, and then pop up multiple coil laying position lines in turn according to the laying direction.
Positioning bullet line
3) Construction of additional layer: For detailed node parts such as gutter, high and low cross-yin angle, water drop mouth, etc., an additional layer of 1.5mm thick EPDM waterproof coiled material shall be made first.
Additional layer paving of running water gutter and wall root shade corner
4) Large-surface paving coil: first lay the coil flat and pre-spread to the position of the positioning elastic line, then fold and lift half of the width along the long side of the coil, roll and coat the coil and the base surface with special adhesive at the same time, brush evenly without exposing the bottom, use amount per square meter (0.3 kg-0.4kg), and air dry for 5-20 minutes; All the adhesive applied by brushing shall be subject to non-stick hands, and the rolled coiled material, and with the rolling along with the timely drive out of the bottom of the coil gas, compaction and bonding coil layer; Then the other half of the coil is lifted in turn, and the base surface and the coil ground are rolled with adhesive at the same time. After drying, the other half of the coil is pushed and bonded. The coil is required to be laid flat and straight, without hollowing, wrinkling, warping and opening.
Coil brushing (left), coil laying (right)
5) above a coil as a starting point, in turn the coil according to the elastic line pre-spread, short side lap seam staggered 500mm, long and short side coil lap width of not less than 100mm, lap edge to brush special lap adhesive bonding and sealing treatment; After bonding, it shall be rolled and compacted with rubber hammer or pressure roller in time.
6) The elevation coiled material shall be turned up not less than 250mm, and sealed after the strip is fixed (this process shall be completed after the construction of the second coiled material).
7) After the large surface waterproof layer is laid and pasted, polyurethane sealant shall be used for edge sealing of each pair of coiled materials, and the width of edge sealing shall not be less than 10mm; After the overlapping edge is sealed and dried, the next coil laying process can be carried out.
The coil shall be smashed with a rubber hammer, and the lap edge shall be sealed.
3. Construction of the second EPDM waterproofing membrane:
1) Repeat the process flow of the first coiled material, starting from the low point of the roof, pre-lay the coiled material by half the width according to the overlapping of the long and short sides of the second coiled material and the first coiled material, and position the elastic line to ensure that the overlapping edges of the two coiled materials are not on the same straight line.
2) First fold and open the coiled material in half. The upper surface of the first coiled material and the bottom surface of the second coiled material shall be evenly coated with adhesive at the same time. After the adhesive is dry and does not stick to hands, the coiled material shall be paved, and the gas on the bottom surface of the coiled material shall be driven out to compact the coiled material to avoid bulging, wrinkling, warping, opening, etc.
Construction of the second coil
3) according to the lap of each pair of coil is not less than 100mm size coated with lap glue, in turn paving each pair of coil, after paving first check whether there is leakage and adhesion is not firm phenomenon, check no quality problems, and then use polyurethane sealant for lap edge sealing treatment. The second coil is paved and pasted, sealed and stored for acceptance.
4. Construction of isolation layer
1) After the waterproof layer is accepted, 200g/㎡ geotextile non-woven fabric isolation layer shall be laid, the isolation layer shall be laid empty, and the overlapping parts shall be fixed by point adhesion, with the overlapping width of the long side not less than 50mm and the short side not less than 70mm;
2) When laying the isolation layer, if the waterproof layer is found to be damaged, repair it in time;
4.Protective layer construction
First of all, according to the design of the vertical and horizontal spacing requirements of the laying of cold-drawn steel bars, cross the binding and fixing, the mixed C20 fine stone concrete paving on the isolation layer, pouring set 6m × 6m grid, seam width of 20mm, with a wooden trowel scraping, check the flatness, and then secondary calendering. Timely maintenance, and then clean the separation seam, seam filling modified asphalt material seal.
5.Deft Node Processing
Waterproof structure of falling water mouth
Deformation joint waterproof structure
Coil take-up treatment
 
Precautions
1. The roof vapor barrier, waterproof layer and insulation layer are strictly prohibited in rainy days, snowy days and weather above level 5 wind construction.
2. The prepared polyurethane waterproof coating should be controlled within 30 minutes.
3. After the construction of each waterproof coating layer is completed, the reaction curing time should be reserved, generally 8h dry, 24h dry; In order to make the coating have sufficient bonding strength and crack resistance, water storage experiment should be done after 36h.
4. Before the construction of EPDM waterproofing membrane, it should be opened and laid on the grass-roots level to make it stretch freely, release stress and avoid the phenomenon of winding drum or ripple inequality.
5. The adhesive shall be applied evenly and without revealing the bottom, so as to avoid local excessive thickness and not drying, resulting in weak bonding or bubbling of local adhesive. In order to ensure the lap width of the coiled material and the smooth paving, the paving shall be carried out in strict accordance with the elastic powder line.
6. In case of bubbling and other phenomena, the coiled material shall be cut open for drying, the adhesive shall be repainted, and then the coil reinforcement layer larger than 100mm at the opening of the coiled material shall be subsidized.
7. After the construction of polymer coiled material waterproof layer is completed, it is forbidden to wear hard-soled shoes to walk, punch or pile up sharp hard objects on it. During the construction of protective layer, special personnel should be assigned to track and supervise to avoid damage to waterproof layer. If there is any damage, it should be repaired in time.
8. After the final setting of the protective layer, it shall be immediately covered and watered for curing for not less than 7d. During the curing period, construction on it is strictly prohibited.
Conclusion
During the construction, after the patient and meticulous construction guidance of Hongyuan waterproof technicians, North Korean workers were able to skillfully construct and master the handling of detailed node parts. Finally, the waterproof project was completed on schedule and won unanimous praise from North Korea.
Since the completion and acceptance of the project in 2014, there has been no leakage. The implementation of the roof waterproofing project of the Liujing Building has brought high-quality waterproof materials, advanced waterproof technology and exquisite construction techniques to the Korean people, and has contributed to the development of friendly relations between the Chinese and Korean people.
Author: Li Guoliang, Qi Shukai